1601 Mariposa Project Schedule

Week of 2/06/17 – Install soil nail shoring system row 1

Week of 2/13/17 – Install soil nail shoring system rows 1 and 2

Week of 2/20/17 – Install soil nail shoring system row 2

Week of 2/27/17 – Warehouse demolition

Week of 3/06/17 – Warehouse demolition

Week of 3/13/17 – Install soil nail shoring system row 3, Warehouse demolition

Week of 3/20/17 – Install soil nail shoring system row 4, Warehouse demolition

Week of 3/27/17 – Warehouse demolition